The Lewin Parkway/ Main Street Overpass was expected to be complete before last Christmas but was delayed due to getting the bearings made. Councillor Vaughn Granter says work there will take another two months.
It’s not a city project, but at Monday night’s regular meeting, Corner Brook council gave an update on the Lewin Parkway and Massey Drive On-Ramp Construction. The Lewin Parkway/ Main Street Overpass was expected to be complete before last Christmas but was delayed due to getting the bearings made. Councillor Vaughn Granter says work there will take another two months. Meanwhile, at the Massey Drive Exit 5 On-Ramp, work is anticipated to be completed in the next two weeks at which time the onramp for the TCH West will be reopened.
Police find drugs, guns, weapons, cash and more in Rocky Harbour; two men facing charges
Government wants higher fines to protect wildlife and no licenses for 5 years for anyone convicted
MUN Student Union to pull funding from their 75-year-old radio station, CHMR, effective June 1st
Corner Brook moves back dates for annual spring cleanup to May4th-29th due to long winter
RCMP NL looking for people to join their Black Engagement Steering Committee