Both projects will last approximately 5-6 weeks.
A couple of big road and construction projects are starting in Corner Brook over the next few days. Today, Marine Contractors started construction on the Curling Street Storm Sewer Project, which is located at the intersection of Curling Street, Griffin Drive, Connors Road and Petries Street. This project is expected to last 6 weeks. On Monday, West Coast Excavating and Equipment Company Ltd. will begin construction at the Old Humber Road Retaining Wall. The lower entrance/exit of Old Humber Road will be closed for the duration of the project which is approximately 5 weeks.